Aircraft Cost Model
Modified RAND DAPCA IV acquisition and flyaway estimates from Raymer Chapter 18, with JET11 aircraft inputs and workbook-specific operating and low-observable extensions.
Inputs and workbook assumptions
Aircraft and program drivers
Labor rates and model factors
Checking the latest BLS CPI-U observation…
BLS CPI Inflation Calculator ↗
BLS defines the CPI-U reference base so that the average price level during 1982–1984 equals 100. On that scale, the 1999 annual average was 166.6. View the BLS historical CPI-U table ↗ Read the BLS CPI questions and answers ↗
The escalation control uses January 1999 as its starting date.
Material mix and fabrication factors
DAPCA coefficients and engine cost
Low-observable treatment assumptions
Cost breakdown
Program cost elements
Estimated labor hours
Low-observable treatment per airframe
Simulation method & assumptions
The acquisition model uses the modified RAND DAPCA IV equations printed in Daniel P. Raymer, Aircraft Design: A Conceptual Approach, Chapter 18, Eqs. 18.1–18.9. JET11 Cost-sheet cells supply aircraft, program, labor-rate, material, engine, operating, and stealth-treatment inputs.
HE = 7.07 · We^0.777 · V^0.894 · Q^0.163 · FmatHT = 8.71 · We^0.777 · V^0.696 · Q^0.263 · FmatHM = 10.72 · We^0.820 · V^0.484 · Q^0.641 · FmatHQ = 0.133 · HM for a non-cargo aircraftCD = 66 · We^0.630 · V^1.3CF = 1807.1 · We^0.325 · V^0.822 · FTA^1.21CM = 16 · We^0.921 · V^0.621 · Q^0.799Ceng = 2251 · (0.043Tmax + 243.25Mmax + 0.969Tt4 − 2228) · NengHE·RE + HT·RT + HM·RM + HQ·RQ + CD + CF + CM + Ceng + CavionicsFmat = Σ(material percent · material factor)Fmat a second time in Cost!C56. Raymer Eq. 18.4 defines non-cargo quality-control hours as 0.133 · HM, so this tool applies the material adjustment only once, through HM. The three coefficients remain editable for sensitivity studies.escalated cost = (1 + EF) × 1999-dollar cost, but replaces its fixed escalation value with BLS CPI-U escalation from January 1999 to the latest available month. The JET11 stealth-treatment rates remain separate 2005-dollar assumptions. This is a conceptual-design estimate, not a budget-quality forecast.Sources. The direct RAND equation source is Ronald W. Hess and H. P. Romanoff, Aircraft Airframe Cost Estimating Relationships: All Mission Types, RAND N-2283/1-AF (1987). The broader methodology is documented in RAND R-3255-AF. The implemented form follows Raymer Chapter 18 and the linked JET11 Cost sheet; the workbook-specific O&M and stealth extensions remain as supplied.